Lee Lake Wells

Customer Profile


Elsinore Valley Municipal Water District (EVMWD) is a sub-agency of the Western Municipal Water District, a member agency of the Metropolitan Water District of Southern California. EVMWD’s powers include providing public water service, planning and developing water supply, and treating, disposing of, and recycling  wastewater. The district has more than 42,000 water, wastewater, and agricultural service connections.

Challenge

Local water resources, including groundwater and surface water from Canyon Lake, satisfied only one-third of the demand in the Elsinore Valley Municipal Water District, forcing the district to make up the difference by importing treated, disinfected water from Lake Skinner and Lake Mathews.

Anticipating rapid population growth over the next two decades, the district needed a near-term plan to increase the supply of potable water while reducing dependence on imported water. They focused on developing groundwater resources in the Lee Lake Groundwater Basin, where they had identified suitable sites for two new groundwater production wells.

The first stage of the project would be to drill test wells, extract representative formation samples, and record reliable groundwater elevation data. The EVMDW turned to Geoscience to manage the project.

Geoscience Solution

Geoscience developed a plan to drill an exploratory borehole near the center of the property for the purposes of evaluating saturated aquifer thickness, production potential, and groundwater quality parameters. The presence of poorly consolidated coarse-grained alluvial material at the site prompted Geoscience to choose the air rotary casing hammer (ARCH) drilling method, which provided representative formation samples critical to the investigation, as well as reliable groundwater elevation data.

Once the team had reached the desired depth, they introduced drilling mud, removed the casing, and performed a suite of geophysical logs. Based on the data obtained from the investigation, they developed a very accurate preliminary design of the production wells, followed by a work plan for the test drilling, field inspection during drilling and testing, and preliminary well designs for the municipal groundwater supply wells. 

In addition, Geoscience staff provided bid support, construction management and observation to drill the initial borehole, and complete isolated aquifer zone testing. 

Customer Results


Based on the results of the zone testing, Geoscience completed the final design and observed well completion, including development of two new groundwater production wells that combined to produce 600 gpm from the aquifer at this location.

Contact Terry Watkins to learn more about this case study.

We are a team of degreed geologists and engineers developing the best solutions for sustainable groundwater. Contact us for reliable results.

    Discover more case studies

    Pismo Beach Regional Groundwater Sustainability Project

    Client Profile The City of Pismo Beach is a member of the Northern Cities Management Area (NCMA) of the Santa Maria Groundwater Basin in San Luis Obispo County, California. There are three major sources of water that supply the NCMA—Lopez Lake (surface water), the State Water Project Coastal Branch (imported water), and groundwater pumping. Each […]

    Read more
    South Orange Coastal Ocean Desalination Project

    Client Profile South Coast Water District (SCWD) provides potable water, recycled water, and wastewater services to 35,000 residents, 1,000 businesses, and 2 million visitors per year in South Orange County, California. Challenge Brackish water occurs in a natural environment that produces a salinity level registering between freshwater and seawater. It occurs in coastal regions where […]

    Read more
    Pure Water Oceanside

    Challenge For decades, the City of Oceanside relied on imported water for more than 85% of its supply to its customers, with less than 15% coming from local supplies in the Mission Ground Water Basin and a 0.7-mgd Recycled Water Facility. Since the turn of the century, the City has been seeking ways to reduce […]

    Read more